Skip to main content
Cabecera areas Actividad

EBPE III, Minera Escondida

Project name

Pump System Electromechanical Assembly for new Bioleaching piles of EBPE III, Minera Escondida Project.

Location

Región de Antofagasta - Antofagasta

Client

Minera Escondida.

Stage

Completed.

Description

Bioleaching Pile Work including assembly, grooving and connections.

S/E SX Works where extend it capability and at S/E Booster including civil Works, stringing conductors, assembly, connections and tests.

A 69kV transmission line from SX S/E to Booster S/E Pumps.

All of the above consider EPC format electromechanical assembly Works.

The length of the project was 23 months finishing at June 2013.